Wan Ren new energy vehicle project is located in Wanshan Economic Development Zone, with a total investment of 2 billion yuan, covers an area of ​​1000 acres, mainly engaged in new energy vehicles and related products, research and development, manufacturing and sales. Since the project started construction in April 2016, the first phase of the project has been progressing smoothly and is expected to be completed and put into use in June 2017.
Wan Ren new energy vehicle project total construction area of ​​130,000 square meters, divided into two phases of construction, a project will be completed stamping, welding, painting, assembly four major production workshop construction. The workers are carrying out the roofing of the office and dormitory, the assembly of the steel column and the steel structure are all completed. The construction of the road network, the wall, the greening and so on is also pushing forward.
The steel structures have been fully lifted and are currently being constructed. Roof panels, wall panels and floor construction are expected to be completed by the end of this month. The equipment is expected to be completed this month. Office building is expected to be completed in July, construction, has now completed two layers of construction, is the construction of third story steel structure.
According to the current construction schedule, the next step mainly for the assembly shop, office buildings, dormitory, road network and other construction projects, to achieve the end of this month will be installed all the assembly plant completed, plant in July 2017 to achieve regular mass production. The project set up a supervision project department, the project implementation of the project supervision.